The Top-Down Method for Estimating Project Time and Cost That

Question 68

Short Answer

The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the ____________ method.

Correct Answer:

verifed

Verified

function point
Explanation: In the softw...