The Top-Down Method of Estimating When the Pooled Experience of Senior

Question 8

Short Answer

The top-down method of estimating when the pooled experience of senior and/or middle managers are used to estimate the total project duration and cost is the _________ method.

Correct Answer:

verifed

Verified

consensus
Explanation: The consensus met...