    Exam 5: Estimating Project Times and Costs
  5. Question
    Costs That Are Not Directly Related to a Specific Project
Solved

Costs That Are Not Directly Related to a Specific Project

Question 3

Question 3

Short Answer

Costs that are not directly related to a specific project, such as advertising, accounting, and senior management's salary, are classified as _____________ costs.

Correct Answer:

verifed

Verified

Related Questions

Q1: The project management structure chosen to manage

Q2: A good starting point for developing time

Q4: Estimates should be made based on _

Q6: Which of the following is NOT one

Q7: The approach to estimating project time and

Q8: The top-down method of estimating when the

Q66: Which of the following is a good

Q69: Accounting would be an example of which

Q70: Estimating the total cost of a project

Q95: Identify the three major categories of project

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines