A Favorable Cost Variance of Significant Magnitude

Question 30

Multiple Choice

A favorable cost variance of significant magnitude:


A) Is the result of exceptional planning.
B) May lead to future improvements in production methods if the variance is investigated to determine its underlying cause(s) .
C) Is strong evidence of excellent operating performance.
D) Is strong evidence of tight financial control.
E) Does not need to be investigated as to its underlying cause.