Multiple Choice
Which of the following tools is helpful in addressing the variance-investigation problem under uncertainty?
A) Statistical control charts.
B) Pay-off tables.
C) Regression analysis.
D) Sensitivity analysis.
E) Run charts.
Correct Answer: