Multiple Choice
An after-action review refers to ________.
A) an online interaction between members of a project and prospective customers after a product has been launched
B) a meeting where members of a team analyze efficiency of an individual before he/she resigns
C) a discussion forum in which members discuss and finalize goals for a project
D) a meeting held after a project has been completed to document what worked well and what did not
Correct Answer:

Verified
Correct Answer:
Verified