Question 1

Multiple Choice

Petroleum Inc.(PI) controls offshore oil leases.It is considering the construction of a deep-sea oil rig at a cost of $500 million.The price of oil is $100/bbl.and extraction costs are $50/bbl.PI expects costs to remain constant.The rig will produce an estimated 1,200,000 bbl.per year forever.The risk-free rate is 10% per year,which is also the cost of capital.(Ignore taxes) .Suppose that oil prices are uncertain and are equally likely to be $120/bbl.or $80/bbl.next year.Calculate today's NPV of the project if it were postponed by one year.


A) +$100 million
B) +$154 million
C) +$170 million
D) +$187 million

Correct Answer: