Multiple Choice
Which of the following examples is NOT a typical or appropriate situation to employ project management?
A) improving a soldering process in an assembly line
B) processing deposits and withdrawals in a bank
C) installing a new accounting application on to a server
D) developing a new medical device for use by clinics