Multiple Choice
Once projects are completed,they will typically yield all of the following results EXCEPT:
A) a unique product,service or result
B) make or buy decisions
C) stakeholders whose interests are affected by the outcome
D) a primary deliverable along with supporting deliverables
Correct Answer:

Verified
Correct Answer:
Verified