Projects Are Considered Successful for All of the Reasons Below

Question 45

Multiple Choice

Projects are considered successful for all of the reasons below EXCEPT:..


A) members of the team learn new skills working on the project.
B) the organization captures lessons learned for future projects.
C) the team has demonstrated heroics to meet project objectives
D) the organization reaps business level benefits.

Correct Answer:

verifed

Verified