True/False
A Work Breakdown Structure must be decomposed at least four levels in order to be effective.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q34: If a problem occurs during project execution,the
Q35: A WBS component is a work element
Q36: Once the plan baseline has been approved
Q37: A typical change request form will include
Q38: Which of the following items best describes
Q39: Which of the following is NOT a
Q40: This technique is an iterative process that identifies
Q41: Work Breakdown Structures can be displayed in
Q42: The Work Breakdown Structure (WBS)is normally developed
Q43: The work component at the lowest level of