Multiple Choice
It is helpful to list requirements and supporting information in a requirements traceability matrix.When requirements are complete,they should meet all of these criteria EXCEPT:
A) identified with the stakeholder who needs it
B) assigned to a team member who will be the requirement owner
C) measurable,so that the value and completion can be verified
D) prioritized so tradeoff decisions can be made if necessary