Multiple Choice
For each component in the Work Breakdown Structure (WBS) ,the WBS dictionary includes all the following fields that will be progressively elaborated EXCEPT:
A) a brief description of the work
B) names of team member(s) responsible for creating the deliverables
C) a list of associated deliverables
D) type of resources needed
Correct Answer:

Verified
Correct Answer:
Verified