Multiple Choice
When estimating resource needs,project teams should consider all the following EXCEPT:
A) support needs such as information systems.
B) the time required to communicate between activities.
C) specific knowledge or skills that are required.
D) scoring models.
Correct Answer:

Verified
Correct Answer:
Verified