Multiple Choice
The staffing management plan addresses all of the following except:
A) how to identify internal and external human resources for the project.
B) how to create RACI charts.
C) how to handle timing issues in building,developing,and releasing the project team.
D) how to determine the availability of human resources for the project
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Project managers must often face the challenge
Q10: When determining resource availability,project managers need only
Q12: Resource leveling is a network scheduling technique
Q18: What is a responsibility assignment matrix (RAM)?
Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q29: The critical chain method is a schedule
Q34: RACI (Responsible,Approve,Consult,Inform)charts go beyond a communication plan
Q34: What should a project manager's considerations be
Q36: When project managers include diverse perspectives in
Q39: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project