Multiple Choice
Project managers must often face the challenge of compressing the project schedule.All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
A) Reduce the project scope and /or quality.
B) Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
C) Use the float in critical path activities
D) Partially overlap sequential activities by using time leads.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Even when a project team does not
Q3: If a project resource is excessively overloaded,it
Q4: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-1 RACI
Q5: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-4 Project
Q6: In order to avoid project delays,project managers
Q7: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 8-3 Programmers
Q8: RACI (Responsible,Accountable,Consult,Inform)charts go beyond a communication plan
Q9: As the project manager identifies potential resources
Q10: When determining resource availability,project managers need only
Q11: Critical chain project management is an alternate