Multiple Choice
All of the following reasons explain why it is better to design quality into processes than to find problems through inspections EXCEPT:
A) The cost of rework can be expensive.
B) The time spent on rework aggravates time pressures that already exist on projects.
C) Some mistakes are likely to reach the customer.
D) The best inspectors should find every variation and defect
Correct Answer:

Verified
Correct Answer:
Verified