Multiple Choice
A reason that the duration on a task may differ from an original duration on a Tracking Gantt chart could be
A) An expected delay.
B) New information on the task.
C) The task has been cancelled.
D) A new budget cycle.
Correct Answer:

Verified
Correct Answer:
Verified