Multiple Choice
Which of the following is NOT a rational reason to reduce project duration?
A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Correct Answer:

Verified
Correct Answer:
Verified