Multiple Choice
Bill is building a project network that involves testing a prototype.He must design the prototype (activity 1) , build the prototype (activity 2) , and test the prototype (activity 3) .Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3.If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1.This is an example of
A) Conditional statements.
B) Looping.
C) Having more than one start node.
D) Good network development.
E) Natural network flow.
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Briefly describe looping and conditional statements and
Q72: Activities that can take place at the
Q75: An activity has a duration of 10
Q76: Information to develop a project network is
Q79: Even though a project costs time and
Q80: When an activity with a long duration
Q81: The delaying of any activity on the
Q91: Which of the following correctly calculates the
Q94: Using free slack does not delay any
Q115: Which of the following correctly calculates the