    Which of the Following Correctly Calculates the Late Start for an Activity
Solved

Which of the Following Correctly Calculates the Late Start for an Activity

Question 115

Question 115

Multiple Choice

Which of the following correctly calculates the late start for an activity?


A) EF - DUR
B) ES - DUR
C) LF - DUR
D) ES - SL
E) LF - SL

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q110: When completing the forward pass, the project

Q111: What is a Gantt chart and what

Q112: Consider the following table of activities A

Q113: Which of the following is true about

Q114: In developing a project network, neither looping

Q116: When completing a forward pass, you carry

Q117: When an activity with a long duration

Q118: Consider the following table of activities A

Q119: Which of the following will correctly calculate

Q120: What is a lag and give an

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines