Multiple Choice
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network.Without a common start node, each path is a
A) Critical path.
B) Parallel path.
C) Dangler path.
D) Multiple start path.
E) Confused path.
Correct Answer:

Verified
Correct Answer:
Verified