Multiple Choice
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
A) The smallest LS of all its immediate successor activities to establish the LF.
B) The largest ES of all its immediate successor activities to establish the LF.
C) The average LS of all its immediate successor activities to establish the LF.
D) The smallest ES of all its immediate successor activities to establish the LF.
E) The largest LS of all its immediate successor activities to establish the LF.
Correct Answer:

Verified
Correct Answer:
Verified
Q34: The WBS identifies dependencies, the sequencing of
Q71: The forward pass through a project network
Q87: Which of the following can be used
Q88: Which of the following is provided by
Q97: The amount of time an activity can
Q98: The activity time estimates used to build
Q101: If a project has more than one
Q103: _ slack must be coordinated with all
Q104: A _ activity is one that has
Q120: What is a lag and give an