Multiple Choice
Refining estimates may be necessary for a number of reasons.For example, resource shortages, in the form of people, equipment, or materials, can extend original estimates.This is a good example of
A) Hidden interaction costs.
B) Things going wrong on a project.
C) Normal conditions not applying.
D) Changes in project scope.
E) The customer not being clear about their expectations.
Correct Answer:

Verified
Correct Answer:
Verified