Multiple Choice
Refining estimates may be necessary for a number of reasons.For example, people working on prototype development needing time to interact with the design engineers after the design is completed is a good example of
A) Hidden interaction costs.
B) Things going wrong on a project.
C) Normal conditions not applying.
D) Changes in project scope.
E) The customer not being clear about their expectations.
Correct Answer: