A Project Requires an Initial Outlay of $10 Million

Question 32

Multiple Choice

A project requires an initial outlay of $10 million.If the cost of capital exceeds the project IRR,then the project has a(n) :


A) positive NPV.
B) negative NPV.
C) acceptable payback period.
D) positive profitability index.