Multiple Choice
If a project's expected rate of return exceeds its opportunity cost of capital,one would expect:
A) the profitability index to be negative.
B) the opportunity cost of capital to be too low.
C) the project to have a positive NPV.
D) the NPV to be zero.
Correct Answer:

Verified
Correct Answer:
Verified