Multiple Choice
What is the NPV for the following project cash flows at a discount rate of 15%? C0 = −$1,000,C1 = $700,C2 = $700.
A) ($308.70)
B) ($138.00)
C) $138.00
D) $308.70
Correct Answer:

Verified
Correct Answer: