Solved

A Project with an IRR That Is Less Than the Opportunity

Question 74

Multiple Choice

A project with an IRR that is less than the opportunity cost of capital should be:


A) accepted for all projects.
B) accepted only for projects with a positive initial cash flow.
C) accepted only for projects with a negative initial cash flow.
D) rejected for all projects.

Correct Answer:

verifed

Verified

Unlock this answer now