Multiple Choice
Following the work breakdown structure,which activity is next?
A) A detailed time schedule is created for each activity.
B) A detailed budget is created for each activity.
C) A time-phased budget is created for the project.
D) None of the above.
Correct Answer:

Verified
Correct Answer:
Verified