Multiple Choice
Which of the following statements is correct?
A) Good project management means removing all slack from the project schedule.
B) Crashing should be spread out and balanced across all the activities on the critical path.
C) Linear programming can be used to find the low-cost solution to complex crashing problems.
D) All of the above.