Multiple Choice
The reason(s) for batch scheduling being a complex management problem is/are
A) irregular flow of units with many starts and stops.
B) layout of the batch process by machine group or skills into work centers.
C) batches result in inventory or people waiting in queues.
D) all of the above.
Correct Answer:

Verified
Correct Answer:
Verified