Question 35

Multiple Choice

Which of the following statements about batch scheduling is INCORRECT?


A) Dispatching is used to determine the job priority at a work center.
B) The priority of a job, once determined, does not change as it progresses through the production process.
C) Finite scheduling in batch systems recognizes the limited processing capacity of the facility and does not allocate more capacity than is available.
D) The theory of constraints argues that scheduling can be improved by increasing capacity at bottleneck operations.