Multiple Choice
In aggregate planning,
A) the concern is over a long-range planning horizon.
B) output levels are set in the face of certain demand.
C) "aggregate" implies that planning is done for a single overall measure of output or at most a few products.
D) firms should never consider overtime, hiring, firing, or subcontracting.
Correct Answer:

Verified
Correct Answer:
Verified