Multiple Choice
The primary concern with having a large positive capacity cushion is
A) reduced customer satisfaction due to the high level of backorders.
B) underutilization of facility capacity.
C) greater likelihood of stock-outs and lost sales.
D) keeping cost of running out in balance with the cost of excess capacity.
Correct Answer:

Verified
Correct Answer:
Verified