True/False
The unit improvement factor for a 60 percent learning curve at 25 units is 0.0933. The first and second timings of a person doing a job are 5 minutes and 3 minutes, respectively. The learning-adjusted time estimate for the unit number 25 is 0.0933 minute.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q36: A company's production process has an 85
Q37: A company's production process has an 80
Q38: The 10<sup>th</sup> repetition of job is timed
Q39: Which of the following computational methods are
Q40: The unit improvement factor for a 60
Q42: A company can produce a small lot
Q43: You time someone completing a single task
Q44: There will be greater improvement in labor
Q45: You time someone completing a single task
Q46: An assumption of learning curves is that