    Consider the Portion of a Project Depicted by This Graph
Solved

Consider the Portion of a Project Depicted by This Graph

Question 55

Question 55

Multiple Choice

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? A)  18 B)  17 C)  13 D)  12 E)  10 What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?


A) 18
B) 17
C) 13
D) 12
E) 10

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: The probability of occurrence of risk events

Q50: Consider the following work breakdown structure:

Q51: Consider the following work breakdown structure:

Q53: Consider the following work breakdown structure:

Q59: Consider the following work breakdown structure:

Q65: There are four activities on the critical

Q74: The project management strategy of injecting additional

Q109: Once a project is approved and underway,

Q113: Which of the following stages is that

Q114: Matrix organizations transfer control of workers to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines