Consider the Following Work Breakdown Structure What Is the Estimated Expected (Mean) Time for Project Completion
Multiple Choice
Consider the following work breakdown structure: What is the estimated expected (mean) time for project completion?
A) 35 weeks
B) 39 weeks
C) 50 weeks
D) 104 weeks
E) 105 weeks
Correct Answer:

Verified