What is the probability that this project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below?  Activity  Mean  Std.Dev. 125123411381\begin{array} { l c c } \text { Activity } & \text { Mean } & \text { Std.Dev. } \\\hline 1 - 2 & 5 & 1 \\2 - 3 & 4 & 1 \\1 - 3 & 8 & 1\end{array}

Correct Answer:

verifed

Verified

Prob(duration exceed...