Consider the Following Work Breakdown Structure What Is the Estimated Expected (Mean) Time for Activity Y
Multiple Choice
Consider the following work breakdown structure: What is the estimated expected (mean) time for activity Y?
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer:

Verified
Correct Answer:
Verified