Solved

Consider the Following Work Breakdown Structure What Is the Probability That This Project Will Be Completed

Question 106

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the probability that this project will be completed within 205 days?


A) 0.6826
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions