In the Project Network Presented Below, Numbers on Each Arrow

Question 67

Essay

In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example, "8,2" indicates an activity with an expected time of 8 and a standard deviation of two weeks. In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example,  8,2  indicates an activity with an expected time of 8 and a standard deviation of two weeks.   For this project, determine each of the following: (A) the activities which are on the critical path (B) the expected project duration (C) the probability that the project will be completed in 29 weeks or less For this project, determine each of the following:
(A) the activities which are on the critical path
(B) the expected project duration
(C) the probability that the project will be completed in 29 weeks or less

Correct Answer:

verifed

Verified

(A) The critical path is 1-3-6...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions