menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Statistics
  3. Study Set
    Operations Management Operations Management
  4. Exam
    Exam 17: Project Management
  5. Question
    Activity E Has an Optimistic Time of 9 Days, a Most
Solved

Activity E Has an Optimistic Time of 9 Days, a Most

Question 6

Question 6

Essay

Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.

Correct Answer:

verifed

Verified

None...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Prepare a crashing plan for the

Q2: Given the network diagram below, determine the

Q3: Consider the following work breakdown structure:

Q7: A project has the activities and

Q8: Consider the following work breakdown structure:

Q11: Which of the following is not a

Q48: Which of the following would probably not

Q81: If two consecutive activities on the same

Q82: When developing probabilistic estimates of project duration,

Q92: There are four activities on the critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines