menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Statistics
  3. Study Set
    Operations Management Study Set 5
  4. Exam
    Exam 17: Project Management
  5. Question
    There Are Four Activities on the Critical Path
Solved

There Are Four Activities on the Critical Path

Question 92

Question 92

Multiple Choice

There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to


A) 2.
B) 4.
C) 8.
D) 16.
E) 64.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q87: Which of the following is not an

Q88: Activity C has an early start time

Q89: The basis for use of the beta

Q90: The higher the node number, the longer

Q91: Consider the portion of a project depicted

Q93: Given this information about activity 3-4: ES

Q94: Deterministic networks use three time estimates-shortest, most

Q95: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q96: The main function of dummy activities is

Q97: Which of the following is not characteristic

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines