Multiple Choice
There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to
A) 2.
B) 4.
C) 8.
D) 16.
E) 64.
Correct Answer:

Verified
Correct Answer:
Verified
Q87: Which of the following is not an
Q88: Activity C has an early start time
Q89: The basis for use of the beta
Q90: The higher the node number, the longer
Q91: Consider the portion of a project depicted
Q93: Given this information about activity 3-4: ES
Q94: Deterministic networks use three time estimates-shortest, most
Q95: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q96: The main function of dummy activities is
Q97: Which of the following is not characteristic