For the Jobs Listed Below, Which Processing Sequence Would Result

Question 88

Multiple Choice

For the jobs listed below, which processing sequence would result using Johnson's rule?  Processing time (hrs)   Job  Center 1  Center 2  a 611 b 128 c 59 d 107\begin{array}{l}\text { Processing time (hrs) }\\\begin{array} { c c c } \hline \text { Job } & \text { Center 1 } & \text { Center 2 } \\\text { a } & 6 & 11 \\\text { b } & 12 & 8 \\\text { c } & 5 & 9 \\\text { d } & 10 & 7\end{array}\end{array}


A) c-a-d-b
B) b-d-a-c
C) a-b-c-d
D) d-c-b-a
E) c-a-b-d

Correct Answer: