Multiple Choice
Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already at X's required resource, the scheduler schedules X to be begun immediately and assumes that X will be done four days from now. This is an example of
A) infinite scheduling.
B) finite scheduling.
C) forward scheduling.
D) backward scheduling.
E) prioritization.
Correct Answer:

Verified
Correct Answer:
Verified