What Is the Optimum Job Sequence for the Jobs Listed

Question 128

Multiple Choice

What is the optimum job sequence for the jobs listed below using Johnson's rule?  Processing time (hrs)   Job  Center 1  Center 2 d1323e2313f1618 g2017\begin{array}{l}\text { Processing time (hrs) }\\\begin{array} { c c c } \text { Job } & \text { Center 1 } & \text { Center 2 } \\\hline \mathrm { d } & 13 & 23 \\\mathrm { e } & 23 & 13 \\\mathrm { f } & 16 & 18 \\\mathrm {~g} & 20 & 17\end{array}\end{array}


A) e-g-f-d
B) d-g-f-e
C) d-f-g-e
D) e-d-f-g
E) f-e-d-g

Correct Answer: