Solved

The Following Table Contains Information About Five Jobs Waiting to Be

Question 120

Multiple Choice

The following table contains information about five jobs waiting to be processed at work center number three.  Job  Processing  Time (hrs)   Hours Until  Due a1415 b1020c1818 d216e421\begin{array} { c c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Hours Until } \\\text { Due }\end{array} \\\hline \mathrm { a } & 14 & 15 \\\mathrm {~b} & 10 & 20 \\\mathrm { c } & 18 & 18 \\\mathrm {~d} & 2 & 16 \\\mathrm { e } & 4 & 21\end{array} Using the EDD rule, the sequence of jobs would be:


A) d-e-b-a-c.
B) a-d-c-b-e.
C) e-d-b-a-c.
D) a-d-c-e-d.
E) e-b-c-d-a.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge