There Are Three Jobs to Be Done and Three Resources

Question 116

Essay

There are three jobs to be done and three resources with which to do them. Each resource will take a specific time to do each job, as shown in the following table:
 Machine  Job  A  B  C 169424433874\begin{array} { l c c c } \quad\quad\quad\quad{ \text { Machine } } \\\begin{array} { l c c c } \text { Job } & \text { A } & \text { B } & \text { C } \\\hline 1 & 6 & 9 & 4 \\2 & 4 & 4 & 3 \\3 & 8 & 7 & 4\end{array}\end{array} What is the result of the row reduction?