Multiple Choice
Refer to this product tree: If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed?
A) 48
B) 144
C) 192
D) 212
E) 272
Correct Answer:

Verified
Correct Answer:
Verified